Washington Oct. 21, 2026
For most of the last century, getting electricity to a new factory was a matter of paperwork and patience. A utility studied the request, built what was needed and spread the cost across its customers. Data center campuses, many of them built on a few hundred acres of farmland, have put that arrangement under its heaviest strain in decades.
Across three of the country’s largest grid regions, technology companies and the developers who build for them have filed requests to connect more than 94 gigawatts of new demand, according to a review of interconnection queues by The Parallel.1Method. We reviewed public queue filings from three regional transmission organizations between January 2025 and September 2026, and removed duplicate requests filed for the same site. That exceeds the peak load of Texas on a summer afternoon. Most of it is for data centers that train and run artificial intelligence models.
Utilities cannot build fast enough to meet it. State regulators must now decide, often for the first time, which customers get served first and who carries the cost if the demand never shows up.
“We are being asked to plan a decade of growth in eighteen months,” said Renata Okoye, director of transmission planning at Calder Ridge Electric, a utility that serves parts of Virginia and Maryland. “The engineering is solvable. The question of who pays is a political one.”
A queue built for power plants
Grid operators designed interconnection queues for generators: wind farms, gas plants and solar fields waiting for permission to sell power onto the grid. Large customers rarely needed a line of their own. A steel mill or a chip fab might add a few hundred megawatts, and utilities could plan for it years ahead.
A single hyperscale campus now asks for a gigawatt or more. Some developers file in several regions at once and keep whichever sites move fastest, a practice planners call speculative load. In one region reviewed by The Parallel, about a third of requested data center capacity came from projects with no signed tenant.2Caveat. The figure relies on developer disclosures to state utility commissions. Some developers treat tenant names as confidential, so the true share may be higher or lower.
Speculative load costs money. If a utility builds a substation or a high-voltage line for a project that later disappears, regulators can pass the bill to households that never asked for it.
Source: Parallel analysis of grid operator queue filings. Illustrative figures for template display.
The bill for load that never arrives
Regulators in at least nine states opened proceedings this year on special tariffs for the largest customers, according to a tally by The Parallel. The proposals share one idea: a company that wants a gigawatt should commit to paying for most of it whether or not it uses it.
The engineering is solvable. The question of who pays is a political one.
Renata Okoye, Calder Ridge Electric
Minimum-demand charges, longer contract terms and upfront collateral now appear in most of the drafts. One proposal before a Midwestern commission would require a 12-year commitment from any customer above 100 megawatts.3Status. The proposal remains under review, with a final order expected in the first quarter of 2027. Contract terms are summarized from the public filing.
Technology companies say they are willing to pay their share, and several have warned in filings that blunt rules could push investment to other states. “Nobody wants residential customers subsidizing data centers,” said Martin Faber, who leads energy policy for the Digital Infrastructure Council, an industry group. “A rule that treats every project as speculative will slow the ones that are real.”
Bringing their own power
Some developers now arrange their own supply. In the past year, hyperscalers have signed agreements to buy output from existing nuclear plants, financed gas turbines on the data center site and reserved capacity from small modular reactors that have not yet been built. Grid operators in two regions have proposed a faster review for projects that arrive with their own generation.4Context. Planners call these co-located or bring-your-own-generation arrangements. Critics argue they can shift reliability costs to other customers when the on-site plant goes offline.
Consumer advocates object to those deals. A nuclear plant that sells its output to a data center stops selling that power to other customers. Advocates in two states have challenged such arrangements, arguing they pull low-carbon power off the shared grid while households keep paying for the lines that connect it.
A county that said yes
In Fallon County, Virginia, a rural county of 41,000 people about ninety minutes from Washington, officials picked a side two years ago. The county approved four data center campuses in 2024. Tax revenue from the first one exceeds what the county collects from every farm and small business combined, said Paul Hinkle, chairman of the board of supervisors.
“That money paid for a new middle school,” Mr. Hinkle said. “It also came with transmission lines through three family farms, and the people who own those farms did not get a vote.”
The local utility has proposed a 500-kilovolt line to serve the campuses. Residents have filed more than 1,400 comments opposing the route, and a state hearing is scheduled for January.
The federal ruling ahead
Federal regulators plan to rule early next year on how utilities should study and charge large loads that connect to the transmission system. Until then, state commissions will keep writing the rules one utility tariff at a time.
AI companies work on a shorter clock. A developer can buy chips in months and raise a building in a year. A new high-voltage line, from planning to energizing, still takes most of a decade.
“The industry learned to move at the speed of software,” Ms. Okoye said. “The grid moves at the speed of steel and permits. Somebody is going to have to adjust, and it will not be the steel.”
CorrectionAn earlier version of this article misstated the capacity of the proposed Fallon County line. It is 500 kilovolts, not 345 kilovolts.
Mara Ellison
Mara Ellison covers energy and AI infrastructure from Washington. She previously reported on utilities and grid reliability for eight years. Reach her securely on Signal at +1 202 555 0147.
Devin Achebe
Devin Achebe is a data reporter on The Parallel’s Data Desk in New York, where he builds the newsroom’s tracker of interconnection queues and utility tariffs.
Comments are closed for this article. We open comments on selected stories for 48 hours after publication. Read our community standards.